Gas turbine availability threatens Mexico's 2030 power generation schedule
The window to secure gas turbines compatible with 2030 closed almost completely during 2026 [D]. In April, GE Vernova spoke of a lead time of about 3 years, without saying whether it ended at shipment or at delivery, and had about 10 GW of capacity left for 2029 and 2030 [V]. In July it described itself as "mostly sold out" through 2030 [V]. In September it was selling slots for delivery in 2032 [V]. The 2026–2030 Development Program of the Federal Electricity Commission (CFE), Mexico's state-owned utility, includes 4,988 MW of firm generation in 8 projects [V]. The firm generation projects considered here use dispatchable technologies that do not depend on immediate solar or wind availability, subject to their operational and fuel supply constraints. Of those MW, 4,868 depend on gas turbines [D]. With a new order in December 2026, a combined-cycle plant would need its turbine within 31 to 37 months to operate in 2030 [E]. Each project's exposure depends on whether it already holds a manufacturing slot and whether the equipment is on its critical path. The public procurement records reviewed do not establish a turbine or engine delivery date for any of the 8 projects [D]. That does not prove the equipment is missing, because the contractor usually buys the turbine and its order to the manufacturer is not public. Evidencing those commitments would change contracting, scheduling, and capital allocation decisions.
0 · Structure of this note
Section 1 presents the 8 projects and the equipment each depends on. Section 2 shows how turbine availability closed in 2026. Section 3 calculates the delivery lead time each project would need and compares it with the market's and with how long CFE's latest plants took. Section 4 gathers what the procurement files show. Section 5 measures the exposed capacity. Section 6 takes the result to Capital Projects and Capital Allocation decisions. Section 7 gathers testable hypotheses and questions.
1 · CFE's 8 firm projects add up to 4,988 MW and depend on gas turbines or engines
The Program's 8 projects are all generation: 5 combined-cycle plants, 2 cogeneration plants, and 1 internal combustion plant [V]. They add up to 4,988 MW, about 16% of the 32 GW of new capacity that the power expansion plan presented by Mexico's government in June 2026 sets for 2030 [D]. The same Program's 175 transmission works are separate, with 22,832 MVA of transformation capacity [V].
Project | Type and location | MW | Target year | Estimated investment |
Tula II (Francisco Pérez Ríos) | Combined cycle · Tula, Hidalgo | ~1,000 | 2030 | USD 1.39 billion |
Altamira | Combined cycle · Tamaulipas | ~581 | 2030 | USD 804 million |
Mazatlán | Combined cycle · Sinaloa | ~575 | 2030 | USD 857 million |
Salamanca II | Combined cycle · Guanajuato | ~498 | 2030 | USD 804 million |
Fifth combined-cycle plant, unidentified | Combined cycle · unconfirmed | ~520 | 2030 | Not published |
Los Cabos | Internal combustion · Baja California Sur | 120 | 2029 | USD 474 million, for 240 MW |
Tula cogeneration | Cogeneration, CFE-owned · Hidalgo | 794 | 2028 | Not published |
Cangrejera cogeneration | Cogeneration, mixed scheme · Veracruz | 900 | 2030 | Not published |
Total | 4,988 | USD 4.33 billion for the 5 projects with a figure |
Source: CFE, 2026–2030 Development Program, Table 1, p. 29, for types, MW, and years [V]. Investment: CFE, presentation of December 17, 2025, as reported in the press and in Proyectos México [H]; there, Los Cabos had 240 MW and was "under reevaluation." The fifth plant is the residual of 3,174 MW minus the 4 named plants [D]; no public source identifies it.
The equipment in question is large. Each combined-cycle plant uses F- or H-class gas turbines of about 250 to 570 MW each, depending on the model [H]. Each plant also needs its step-up transformer, which connects its generator to the grid. The grid also needs power transformers for 230 and 400 kV substations.
Another 1,662 MW come from earlier plans and are not added [H]. They are the Guadalajara combined-cycle plant, of 934 MW according to the February 2025 Strengthening Plan, and the Salina Cruz cogeneration plant, of 728 MW. Guadalajara already has an award recommendation for its works (section 4). At 934 MW it does not match the ~520 MW of the fifth plant, so this note cannot confirm that it is that project.
This note reconciles with PE-7 in one sentence. The 2.2 GW of 100% CFE combined-cycle plants without works started that PE-7 cites equal the 3,174 MW of the 5 plants minus the ~1,000 MW of Tula II, which is already under construction [D].
2 · Turbine availability closed during 2026, while Mexico needed to secure turbines
3 manufacturers dominate large gas turbines. GE Vernova is American, Siemens Energy is German, and Mitsubishi Power is the turbine brand of Japan's Mitsubishi Heavy Industries. Behind them come Italy's Ansaldo Energia, Korea's Doosan Enerbility, and Chinese manufacturers.
GE Vernova shows how the market went from having slots to not having them. Its aggregate gas turbine book, comprising firm orders and factory slot reservations, grew from 83 GW at the end of 2025 to 122 GW in September 2026 [V]. It expects to close 2026 with at least 130 GW [V].
Figure 1 · From March to September 2026, GE Vernova's firm turbine orders grew 45.5% and its aggregate book 22% [D]

The aggregate book adds firm orders and factory slot reservations, and does not by itself equal exhausted manufacturing capacity. GE Vernova published the split for March, June, and September 2026; this figure does not estimate it for 2025. Firm orders: from 44 to 64 GW, +45.5%; aggregate book: from 100 to 122 GW, +22% [D]. The change in balances does not measure how many reservations converted to orders. Year-end targets are the manufacturer's commercial expectations, not commitments.
Date of statement | What GE Vernova said | What it means for a new order |
April 22, 2026 | Lead time of about 3 years, with no specified end event. About 10 GW of capacity left across 2029 and 2030. Customers wanted 2030 more than 2029, because of their contractors' schedules [V] | Residual availability for 2029–2030 |
July 22, 2026 | "Mostly sold out" through 2030. Expects to have sold more than half of its 30 GW of 2031 output by year-end [V] | 2030 practically closed |
September 16, 2026 | Already sold several slots for 2032 delivery. Added 12 GW of capacity for 2030 and 2031, all of it in negotiation [V] | Demand extends to newly announced capacity |
October 28, 2026 | Aggregate book of 122 GW; target of at least 130 GW by the end of 2026, as a commercial expectation [V] | The book keeps growing |
Sources: GE Vernova, transcripts of the earnings calls of April 22 and July 22, 2026, transcript of its appearance at the Morgan Stanley conference of September 16, 2026, and Form 8-K of October 28, 2026 [V].
This note separates historical from current availability. The 3-year lead time of April describes a market that still had slots in 2029–2030. At this note's cutoff, a new order for a large GE Vernova turbine would get a production slot in 2031 or later [D]. GE Vernova speaks of production slots, not of on-site delivery dates. That does not rule out stray slots from cancellations, capacity additions, or other manufacturers.
Siemens Energy and Mitsubishi describe a similar constraint. In June 2026, a Siemens Energy executive said the company's capacity was booked through its fiscal 2028, and that 2029 and 2030 slots were filling very quickly, according to S&P Global [H]. In August, its CFO said lead times ran 3 years or more, without stating the end event [H]. At the end of its fiscal year, in September 2026, Siemens Energy had 104 GW committed: 65 GW in firm orders and 39 GW in reservations [H]. Mitsubishi had 35 GW in large-turbine orders as of June 2026 [H]. In October it said demand is pushing its deliveries to 2031, according to Bloomberg [H].
Prices rose with scarcity. The global average price of gas turbines rose more than 30% since 2021, according to the International Energy Agency (IEA) [V]. The price of transformers rose 75% since 2019 [V]. New turbine orders in the United States reached a 25-year high in 2025 [V].
From order to delivery, a large power transformer took about 2.5 years on average in mid-2025, and can take up to 4. Wood Mackenzie measured 128 weeks for power transformers and 144 weeks for step-up transformers in its second-quarter 2025 survey [H]. The IEA found that securing a large one can take up to 4 years [V].
CFE competes for the same factory slot, including inside Mexico. Large transformers are made by Hitachi Energy (Switzerland and Japan), Siemens Energy (Germany), GE Vernova (United States), HD Hyundai Electric and Hyosung Heavy Industries (Korea), and TBEA and China XD (China). This note includes no market shares, because it found no source it can verify. 2 of those manufacturers produce in Mexico:
GE Vernova bought in February 2026 the 50% it did not own of Prolec GE, a transformer maker from Nuevo León, for USD 5.25 billion [V]. Prolec GE sells to CFE and to the U.S. market [H]
WEG, a Brazilian company, makes power transformers in Huehuetoca, State of Mexico, and in Tizayuca, Hidalgo [H]. Its Huehuetoca plant delivered 400 kV transformers to CFE for the Los Mochis substation [V]. WEG plans to invest USD 250 million in Mexico through 2030, mainly to export to North America [H]
U.S. demand rises in 2 ways. In August 2026, about 180 GW of gas-fired generation was planned there for data centers [V]. On August 26, 2026, Executive Order 14420 allowed the U.S. Department of Energy to prohibit electrical equipment from designated foreign entities, including Chinese companies [V]. The order covers substation transformers and generation turbines [V]. That pushes U.S. buyers toward manufacturers such as those producing in Mexico [H].
3 · To operate in 2030, a plant without a prior slot would need a delivery lead time the market no longer offers
The break-even test calculates the delivery lead time each project would need to operate in its target year. This note assumes the order is signed on December 1, 2026, and that the project must operate by December 31 of its target year [E]. That day is the end of the year CFE gives, not a contractual date. Erection and commissioning are subtracted from the time available: 12 to 18 months for combined-cycle and cogeneration plants, with 15 as the central case, and 6 to 12 months for engines. These erection and commissioning periods are an InsightIA assumption [E].
3 events are measured separately. Shipment is the turbine leaving the factory. Delivery is its arrival on site. Commissioning ends in the plant's commercial operation. GE Vernova's CEO said in July 2026 that commissioning a large turbine can take another 18 months on site after shipment [V]. That reference supports the 18-month end of the erection assumption.
Figure 2 · With a new order, the 5 combined-cycle plants and the Cangrejera cogeneration plant would need their turbine on site within 31 to 37 months; the lead time GE Vernova states does not say whether it ends at shipment or on site [E]

Calculation: months between December 1, 2026, and December 31 of the target year, minus 12 to 18 months of erection (6 to 12 for engines). For 2030 there are 49 months available: 49 − 18 = 31 and 49 − 12 = 37 [D]. The bars measure the lead time to on-site delivery. The lines are lead times stated by GE Vernova, whose end event is not evidenced: they are not directly comparable with the bars. Production slots from 2031 are indicative availability stated by the manufacturer, not a binding offer for projects in Mexico. Illustrative scenario, not a forecast.
Without a prior manufacturing slot, the test depends on which lead time is taken as current and on the event where it ends [E]. If April's 36 months ended with the turbine on site, the 2030 plants could meet their target only under the 12-month erection and commissioning assumption. If they end at shipment, the lead time to site is longer, and this note does not estimate it. With production slots from 2031, none arrives. Los Cabos would pass with engines if their delivery lead time were 12 to 24 months [E]. When the contractor or CFE already holds a reserved slot, the deciding date is the on-site delivery date associated with that slot, if it is compatible with the critical path.
The 2 matrices below measure 2 different things [E]. The first counts the turbine MW that would miss their own target year. The second counts the MW that would not be operating on December 31, 2030. The difference is the Tula cogeneration plant: with a 2028 target, it can miss its year and still operate in 2030.
Delivery lead time | MW missing their target year: 12-month erection | 15 months | 18 months |
24 months | 794 | 794 | 794 |
30 months | 794 | 794 | 794 |
36 months | 794 | 4,868 | 4,868 |
48 months or more | 4,868 | 4,868 | 4,868 |
Delivery lead time | MW not operating on December 31, 2030: 12-month erection | 15 months | 18 months |
24 months | 0 | 0 | 0 |
30 months | 0 | 0 | 0 |
36 months | 0 | 4,868 | 4,868 |
48 months or more | 4,868 | 4,868 | 4,868 |
MW of the 7 turbine projects, with an order signed on December 1, 2026, and no prior slot. 794 MW is the Tula cogeneration plant. 4,868 MW are the 7 projects. The 120 MW of Los Cabos are excluded because the matrices cover gas turbine projects only. Illustrative scenario, not a forecast.
The cell that matters most is 36 months. At that lead time, going from 12 to 15 months of erection leaves the 4,868 MW of turbines not operating at the end of 2030. That is why it matters so much whether April's lead time is still available to Mexico and whether it ends at shipment or on site.
CFE's latest plants show that construction delays add to equipment delays. Of the 5 combined-cycle plants CFE began building in 2021–2022, 4 had a published scheduled date [H]:
CFE plant | Scheduled date | Commercial operation | Delay |
Mérida (Elvia Carrillo Puerto) | November 1, 2024 | May 12, 2026 | ~18 months |
González Ortega, Mexicali | March 2025 | May 17, 2026 | ~14 months |
San Luis Río Colorado | January 31, 2025 | Not evidenced in the sources reviewed | No data |
Tuxpan Phase I | May 30, 2025 | Not evidenced in the sources reviewed | No data |
Sources: CFE scheduled dates, published in 2023, and operation dates announced by CFE in 2026, both as reported in the press [H]. Riviera Maya (Valladolid) is left out because this note did not find its original scheduled date. Delay: months between the 2 dates [D].
The 2 plants with a documented operation date arrived 14 and 18 months late. The other 2 have no operation date evidenced in the sources reviewed. 4 cases are not enough to estimate a base probability, but they do show that CFE's construction schedule also slips. Those plants bought their equipment when the turbine market still had slots.
4 · Procurement files show works under way, but none evidences the turbine
In CFE plants, the purchase chain usually runs from CFE to the contractor and from the contractor to the manufacturer. CFE contracts the works on a turnkey, lump-sum basis. The contractor buys the turbine. The evidence that matters is the contractor's order to the manufacturer, with its delivery date. In mixed projects, such as the Cangrejera cogeneration plant, the private partner buys.
This note uses 3 phrases for progress in securing equipment. "Equipment contracted" is a contract with a delivery date. "Equipment reserved" is a factory slot with a validity period. "No contract or reservation in sight" is what does not appear in the documents reviewed, and does not mean it does not exist.
On November 25, 2026, InsightIA reviewed CFE's tender microsite and Compras MX, the federal public procurement system.
Project | What the file shows | Progress in securing equipment |
Tula II | Contract signed on December 9, 2025, and site handed over on December 15, according to CFE [H]. The press attributes the works to Mota-Engil for MXN 26 billion, over 47 months [H] | No contract or reservation in sight for the turbine. Works are under way |
Guadalajara (earlier plans) | Tender CFE-0004-CACOT-0005-2026. On November 18, 2026, CFE issued its award recommendation to the ICA consortium: turnkey, lump-sum works for USD 1.51 billion, with 1,260 days of execution. It was the only compliant bid [V]. The tender schedule sets contract signing for November 30, 2026, and plant acceptance for May 13, 2030 [V] | No contract or reservation in sight for the turbine. The construction contract is not yet signed |
Los Cabos | Tender CFE-0004-CACOT-0004-2026 for an internal combustion plant with a solar plant. On November 5, 2026, CFE found all 4 technical bids non-compliant. The bids included Wärtsilä and Hyundai engines [V] | No award in the tender reviewed. Separate engine supply arrangements have not been established by the records reviewed |
Salamanca II | CFE binding market inquiry and transmission reinforcement contract of July 9, 2026 [V]. No main works tender on the microsite | No contract or reservation in sight |
Altamira | No tender identified on the microsite. Contract signing has not been verified in the sources reviewed | No contract or reservation in sight |
Mazatlán, fifth plant, and the 2 cogeneration plants | No tender on the microsite | No contract or reservation in sight |
Source: CFE tender microsite (msc.cfe.mx), files downloaded on November 25, 2026 [V]. The microsite lists the Guadalajara tender as "Adjudicado" with the November 18 recommendation; this note found no signed contract published. Amount: USD 1,506,121,233, rounded. Compras MX does not publish CFE tenders: searches for "transformador" (276 concluded results), "ciclo combinado," "turbina de gas," and "motogenerador" returned no CFE procedure.
2 data points could change the thesis and remain unconfirmed. A trade outlet reported in January 2026 GE Vernova turbine contracts for 4 CFE combined-cycle plants, without confirmation from the manufacturer or CFE [H]. If those contracts exist and their delivery fits the erection schedule, those plants would pass the test in section 3. The precedent exists: CFE bought a Siemens SGT6-8000H turbine for its Empalme plant by direct award, for MXN 1.16 billion [V].
In transmission, a construction contract and transformer supply are different things. Of the 22,832 MVA, 3,508 MVA already operate [V]. Another 12,780 MVA (56%) are in projects for which construction contracts had not been awarded at the May 2026 cutoff [D]. Including works under construction, 19,323 MVA (85%) remain outside the operating stage and require contractual verification of transformer supply [D]. The microsite shows transmission tenders with transformation scope in October and November 2026, but no batch purchase of transformers [V].
Figure 3 · 12,780 MVA of CFE's new transformation capacity are in projects without awarded construction contracts, and 19,323 MVA require contractual verification of supply [D]

The November 25, 2026, search found no batch purchase of transformers; it did not review the supply files of the 123 pending works one by one. The 5 stages in CFE's Table 15 add up to 22,831 MVA, and the published total is 22,832. CFE rounds each stage to whole MVA, so the sum loses 1 MVA; this note uses the published total and the figures by stage [D].
5 · 4,868 MW of turbines are exposed to equipment procurement, and 19,323 MVA of transformation require contractual verification
Exposed capacity is not a shortfall. It is capacity whose commercial operation date depends on equipment no one has evidenced. It can arrive on time if its contractor already has secured supply.
In generation, the exposed capacity is 4,868 MW [D]. The 4,868 MW correspond to the seven projects that depend on gas turbines. The 120 MW of Los Cabos are analyzed separately, because they use engines with a different supply chain and lead times. Their exclusion does not imply that their schedule is secured. How much of that capacity would not be operating at the end of 2030 depends on the current lead time and on erection. It ranges from 0 MW, with 36 months of delivery and 12 of erection, to 4,868 MW, with 48 months or more [E]. A project reduces its exposure when it evidences secured supply, with sufficient evidence and an on-site delivery date compatible with its schedule. A firm order evidences it more strongly than a binding reservation, which depends on its conversion terms. For Tula II, with 15 months of erection, on-site delivery would have to occur by September 2029 at the latest [D].
The works not yet in operation add up to 19,323 MVA. The documents reviewed do not allow the supply of their transformers to be evidenced individually. This figure delimits the universe that requires contractual verification; it is not an estimate of capacity that will arrive late. Within that universe, 12,780 MVA are in projects without awarded construction contracts. With 36 months of delivery and 6 of erection, they would have to sign by mid-2027 at the latest [E].
A delay in firm generation would hit the evening and night hours. New solar covers the day, and the evening peak depends on firm plants and on storage [H]. A delay in the combined-cycle plants would lower the reserve margin in exactly those hours and raise the value of 3- to 4-hour storage [H]. PE-9 measures how heat and air conditioning push that peak.
6 · CFE, its contractors, and those who finance them should evidence the manufacturing slot before allocating capital
Securing the equipment can decide each project's schedule, if its financing is resolved and the equipment is on its critical path [H]. In a project without financing, or with a longer constraint such as gas or interconnection, the turbine is not what sets the date. Each actor has a concrete question about its equipment:
Actor | Capital Projects decision |
CFE as turbine buyer | Evidence the manufacturing slot of each plant, or secure it through a framework agreement or a batch reservation |
CFE Transmission | Buy transformers in batches or leave them to project-by-project procurement |
Turnkey contractor of a CFE plant | Evidence to CFE and to its bank the order to the manufacturer, with an enforceable delivery date |
Partner in a mixed project | Secure the turbine and the step-up transformer before financial close |
Project fund or bank | Ask in its review for the progress in securing each piece of equipment |
This yields alternatives for allocating capital, which are not yet recommendations [H]. One is to pay for factory slot reservations before each project's close. Another is to finance a transformer inventory before the works are awarded. A third is to tie the price and tenor of debt to the progress in securing equipment. Each needs evidence that is missing today: who owns the equipment, how risks are shared, whether the instrument is eligible, and what it costs compared with project-by-project procurement.
A Capital Projects Decision System would treat equipment as a schedule constraint, with its grade of evidence [H]. It would compare each project's required on-site delivery date with the delivery schedule associated with its manufacturing slot. It would show which projects secure equipment now, which are rescheduled, and which can wait. Only then would it allocate reservation capital to the projects where the commercial operation date changes.
InsightIA builds Capital Projects Decision Systems that integrate the supply of critical equipment with each project's execution schedule. They quantify how much commercial operation can be brought forward by securing a piece of equipment and compare that value with the cost and risk of the early commitment. Capital Allocation makes it possible to prioritize those commitments across projects.
7 · Contracts with manufacturers would make it possible to test the hypotheses
Hypothesis | Would confirm it | Would weaken it |
Securing equipment decides the commercial operation date of CFE's plants, if their financing is resolved and the equipment is on their critical path | Orders to manufacturers with deliveries in 2030 or later | Orders with an assigned turbine and delivery before October 2029 |
A new order for a large turbine gets a production slot in 2031 or later | Manufacturer offers to Mexico with production slots in 2031 or later | Offers to Mexico with production slots in 2029 or 2030 |
Transformer purchasing is project-by-project procurement | 2027 works waiting for a transformer | A published CFE batch purchase |
If you are a developer or contractor
Do you have equipment contracted, equipment reserved, or no contract or reservation today for each turbine and transformer in your projects?
Does your order to the manufacturer cover the same date as your contract with CFE?
Who pays for the reservation if the project does not close?
If you finance projects
Does your review ask for the order to the manufacturer for the turbine and the step-up transformer?
Would you finance an equipment reservation before close? With what collateral?
What changes in the price of your debt if the equipment is contracted and not just reserved?
Evidence marks: [V] verified in the primary source · [D] derived, with the calculation shown · [E] estimate with stated assumptions · [H] hypothesis or secondary-source data. "No contract or reservation in sight" means the recorded search found no contractual evidence; it does not mean none exists.
InsightIA analysis.
Sources
IEA, World Energy Outlook 2026, November 2026, pp. 22, 84, 123, 124, and 402 · https://www.iea.org/reports/world-energy-outlook-2026
CFE, 2026–2030 Development Program, July 2026, Tables 1 and 15 · https://www.cfe.gob.mx/finanzas/Documents/ProgramaDesarrollo-26.pdf
CFE, priority projects presentation, December 17, 2025, in Proyectos México · https://www.proyectosmexico.gob.mx/en/proyecto_inversion/plan-de-fortalecimiento-y-expansion-del-sistema-electrico-nacional-generacion/
CFE, tender microsite, files CFE-0004-CACOT-0005-2026 (Guadalajara) and CFE-0004-CACOT-0004-2026 (Los Cabos) · https://msc.cfe.mx
GE Vernova, first-quarter 2026 earnings call transcript, April 22, 2026 · https://www.gevernova.com/sites/default/files/gev_webcast_transcript_04222026.pdf
GE Vernova, second-quarter 2026 earnings call transcript, July 22, 2026 · https://www.gevernova.com/sites/default/files/gev_webcast_transcript_07222026.pdf
GE Vernova, Morgan Stanley Laguna Conference transcript, September 16, 2026 · https://www.gevernova.com/sites/default/files/ge-vernova-morgan-stanley-laguna-conference-2026-transcript.pdf
GE Vernova, Form 8-K for the second quarter of 2026, July 22, 2026, March split · https://www.sec.gov/Archives/edgar/data/0001996810/000199681026000147/gevpressrelease2q26.htm
GE Vernova, Form 8-K for the third quarter of 2026, October 28, 2026 · https://www.sec.gov/Archives/edgar/data/0001996810/000199681026000162/gevpressrelease3q26.htm
GE Vernova, Form 10-Q for the first quarter of 2026, Prolec GE acquisition · https://www.sec.gov/Archives/edgar/data/0001996810/000199681026000064/gev-20260331.htm
S&P Global, "Siemens Energy lifts global gas turbine outlook on data center demand," June 30, 2026 · https://www.spglobal.com/energy/en/news-research/latest-news/electric-power/063026-siemens-energy-lifts-global-gas-turbine-outlook-on-data-center-demand
Utility Dive, Siemens Energy backlog and lead times, August 2026 · https://www.utilitydive.com/news/siemens-gas-turbine-backlog-nears-70-gw-as-company-expands-manufacturing/827390/
Turbomachinery International, Siemens Energy fiscal 2026 results, November 13, 2026 · https://www.turbomachinerymag.com/view/siemens-energy-fy2026-record-backlog-164-billion-gas-services-orders
Utility Dive, Mitsubishi large-turbine backlog, August 2026 · https://www.utilitydive.com/news/mitsubishi-gas-turbine-backlog-earnings/827761/
Bloomberg, "High Demand for Gas Turbines Is Pushing Out Deliveries to 2031, Mitsubishi Power Says," October 27, 2026
Wood Mackenzie, transformer lead-time survey for the second quarter of 2025, in EEPower · https://eepower.com/tech-insights/transformer-supply-chain-woes-persist-as-energy-demand-grows/
The White House, Executive Order 14420, August 26, 2026 · https://www.whitehouse.gov/presidential-actions/2026/08/declaring-a-national-emergency-to-secure-the-united-states-bulk-power-system/
WEG, 400 kV transformers for CFE from Huehuetoca · https://www.weg.net/institutional/BI/pt/news/produtos-e-solucoes/400-kv-power-transformer-weg-can-do-it
Government of Mexico, 32 GW power expansion plan to 2030, June 24, 2026, in Enerdata · https://www.enerdata.net/publications/daily-energy-news/mexicos-new-power-expansion-plan-targets-22-gw-new-renewable-capacity.html
CFE, scheduled and operation dates of the Mérida, González Ortega, San Luis Río Colorado, and Tuxpan Phase I plants, in the press (Energy & Commerce, 2023; Diario de Yucatán and El Imparcial, 2026)
CFE, Call for a binding market inquiry, Salamanca II combined-cycle plant · https://www.cfe.gob.mx/Documents/Convocatoria_ICM_Vinculante_CCC_Salamanca.pdf
Plan for the Strengthening and Expansion of the National Electric System 2025–2030, February 5, 2025