Colombia will pay 15% of substation caps with 4 bidders, up to 95% with 1
COLOMBIA · POWER, ENERGY & ENVIRONMENTAL TRANSITION
A Decision Signal by InsightIA · November 2026
UPME called 6 electricity transmission tenders in 2026. Three opened price envelopes and 3 did not. The 3 that did tender a substation with its associated transmission lines, and in all 3 the CREG set a maximum award value beforehand. Bids are measured as the present value of Expected Annual Revenue over 25 years.
Tender | Voltage | Bids that moved to the price stage | Lowest bid | CREG cap | Bid over cap |
UPME 02-2026 · Nueva Subestación Corzo | 500 kV | 4 of 4 | 25.5 million USD | 170 million USD | 15.0% |
UPME STR 01-2026 · Nueva Lorica | 110 kV | 1 of 2 | 623 billion COP | 654 billion COP | 95.3% |
UPME STR 02-2026 · Nueva Bosconia | 110 kV | 1 of 2 | 136 billion COP | 176 billion COP | 77.0% |
Corzo was the only tender with competition. Grupo Energía Bogotá bid 25.5 million USD, Alupar Colombia 38.9 million, PEL Panamá Estate 47.2 million, and ISA 93.7 million. UPME awarded the project to Grupo Energía Bogotá on September 29, 2026, 14 days after the bid submission hearing.
The 2 works at 110 kV went the other way. On July 31, in Nueva Lorica, ENELCA's bid was declared non-conforming on technical experience. Consorcio Sigma Energía's remained the only valid one, at 95.3% of the cap. In Nueva Bosconia, Consorcio Energía G5's bid was declared non-conforming and Eléctricas de Medellín's remained the only one, at 77.0%. Both then moved to the counterproposal period. In Nueva Lorica, the counterproposal's technical envelope entered evaluation on August 11, and the file also records a tutela, the Colombian constitutional injunction. In Nueva Bosconia, the counterproposal hearing was suspended on September 18: the committee asked for more than 20 business days and announced that the new date would come by addendum. Neither work is awarded in the published records.
The other 3 tenders of 2026 have not opened investor bids: Sahagún 500 kV, Heliconia 500/230 kV, and the Nueva Galapa and Nueva Palermo 110 kV substations. All 3 have a supervising engineer in process or selected.
Our reading: the CREG cap bounded the price, and competition determined it. Where 4 companies reached the price stage, the work will be paid at 15.0% of the cap. Where a single valid bid remained, the price landed between 77% and 95% of the cap. Anyone deciding today whether to enter a 110 kV tender faces one question: how many competitors will reach the price stage. That count is made across the 6 tenders of the year, not one's own. It is what a Decision System for Capital Allocation puts in front of the decision before bid capital is committed.