top of page

The Dominican Republic relaunches at 900 MW the tender that left 274 MW uncontracted

2 days ago
2 min read

The Consejo Unificado de las Empresas Distribuidoras de Electricidad (unified council of the distribution companies), which coordinates joint purchases for Edenorte, Edesur and Edeeste, asked for approval of new tender terms on November 4. The Superintendencia de Electricidad, the Dominican electricity regulator, set them on November 19 through Resolución SIE-155-2026-LCE. Tender EDES-LP-NGR-01-2026 will contract up to 900 MW of solar and wind plants with own storage, in a single block, under 180-month contracts.

The previous process was awarded in April. The tender committee awarded 5 bids on April 15, 2026. The regulator later approved each winner's contracts.

Winner

Net nominal capacity, in MW

Resolution approving its contracts

Mella Solar Power (MSP1), S.R.L.

99.00

SIE-064-2026-LCE

Parque Taíno I, S.R.L.

84.70

SIE-062-2026-LCE

Empresa Generadora de Electricidad Haina, S.A.

49.50

SIE-060-2026-LCE

Empresa Generadora de Electricidad Haina, S.A.

48.29

SIE-061-2026-LCE

Galileo Energía, S.R.L.

44.20

SIE-063-2026-LCE

Total

325.69


The 2025 terms offered up to 600 MW. 274.31 MW, or 45.7% of that ceiling, went uncontracted. Three participants challenged the results before the regulator, which declared their appeals inadmissible on June 10, 2026, and upheld the committee's decisions. One of them attributed the shortfall to the award formula and to a parameter called CMAinf. The regulator answered that the terms set a maximum capacity, with no obligation to award all of it, and that they provided for a partial award.

The 2026 resolution publishes 15 conditions of the tender: 7 characteristics of the supply and 8 technical requirements for the storage. Twelve repeat the 2025 text word for word. Three change. One of them, the capacity to contract, changes 2 figures: the ceiling and the minimum per project.

Condition

2025 tender

2026 tender

Maximum capacity to contract

600 MW

900 MW

Minimum and maximum per project

20 MW and 300 MW

2 MW and 300 MW

Ramp-rate control, per hour

20% of nominal capacity

25%

Definitive concession in force

when the terms are published

before the prequalification phase

The other 7 storage requirements do not change. Every plant must keep 4 hours of storage for the whole contract, offer fast frequency response (synthetic inertia), provide black start and hold the grid's voltage and frequency reference.

Our reading: the 3 changes widen who may bid. None of the 5 winning bids came near the 20 MW minimum. The smallest was 44.20 MW, 2.21 times that floor. Lowering the minimum to 2 MW opens the tender to projects a tenth the size of the previous limit, but does not address what left 274.31 MW uncontracted.

The resolution publishes neither the award formula nor the process calendar. The terms are acquired only through the mechanism they themselves set, and open to public consultation once the acquisition period ends. We cannot confirm whether the 2026 formula repeats the 2025 one.

A Capital Allocation Decision System would value entry by what the previous process awarded and by the formula in force, and not by the published ceiling. That is our hypothesis, and it falls if the 2026 formula turns out to differ from the 2025 one.

InsightIA analysis.

Recent Posts

bottom of page