Out of 223 registrations, Mexico granted 6 solar permits for 649 MW with mandatory batteries

5 days ago
3 min read

MEXICO · POWER, ENERGY & ENVIRONMENTAL TRANSITION

Mexico's Ministry of Energy published the Second Call for Projects in the Diario Oficial de la Federación (the federal gazette) on May 11, 2026. It opened a priority route for new generation projects of 0.7 MW or more, aligned with binding planning, the government plan that sets where and when the power system needs new capacity. The Comisión Nacional de Energía, the energy regulator, evaluates and resolves the applications. The Centro Nacional de Control de Energía, the system operator, runs the interconnection studies.

On November 6 the regulator approved 6 solar generation permits: 649 MW of net capacity, which correspond to 751 MW of installed capacity. Estimated investment runs around USD 750 million and estimated annual output, 1,881 GWh. Occidental holds 350 MW, Oriental 289, and Noreste 10. Of the capacity, 37% enters operation in 2028 and the remaining 63% in 2029.

Stage

2026 dates

Projects

Fall against the previous stage

Expression of interest

May 13 to 29

223

—

Payment or revalidation of interconnection studies

July 6 to 15

71

−152 · 68%

Filing of the permit application

July 16 to August 18

57

−14 · 20%

Signature of the works' cost acceptance

October 9 to 28

10

−47 · 82%

Permits granted

November 6

6

−4 · 40%

The call set 2 technical conditions that explain the profile of what was approved. Every plant had to bring a storage system of at least 30% of its capacity and at least 3 hours of duration. Its commercial operation date had to be the earliest possible between 2027 and the first half of 2030.

The stage that cuts the most candidates, in proportion, is the acceptance of works. The system operator notifies each applicant of its study results through the electronic window. The same document states the cost in pesos of the reinforcement works and interconnection works the applicant must cover if the permit comes. When those works serve 2 or more projects, the cost is split pro rata by each one's MW. Whoever decides to continue files the Formato Aceptación de Obras (works acceptance form), which the call defines as a necessary condition to continue and obtain the permit. Whoever does not file it is deemed to have withdrawn. If one of the group does not sign, the operator re-evaluates the cost within 5 business days and notifies the new split to the others.

Our reading: the filter of the call is the grid cost. 47 of the 57 applications did not sign that cost. A developer learns it only after paying for the studies and applying for the permit, and the amount changes if another project in its group withdraws. The signature obliges payment only if the permit comes; 4 of the 10 that signed did not receive it.

The official publication identifies the 6 permits by folio number and region, with no company name, no capacity per project, and no battery size. Whoever wants to know who won will not find it in the official source.

A Capital Projects Decision System would estimate the grid cost of each site before entering the call, and not upon receiving the notification. That is our hypothesis, and it falls if the notified costs turn out close to what a developer could already estimate with public data.

InsightIA analysis.