Guatemala's distributors contracted 82% of their 2030 requirement and 90% of their 2033 requirement
GUATEMALA · POWER, ENERGY & ENVIRONMENTAL TRANSITION
A Decision Signal by InsightIA · November 2026
The PEG-5-2025 bidding documents, approved by the CNEE —Guatemala's electricity regulator— through resolution CNEE-108-2025 and 4 addenda, did not call for 1,400 MW at once. They called for one step per supply-start year. The Award Report measures the result against that step.
Seasonal year | Capacity tendered (MW) | Capacity awarded (MW) | Virtual bidder (MW) | Coverage |
2030 | 1,000 | 818.64 | 181 | 81.9% |
2031 | 1,000 | 931.34 | 69 | 93.1% |
2032 | 1,300 | 1,177.43 | 123 | 90.6% |
2033 to 2044 | 1,400 | 1,258.39 | 142 | 89.9% |
The virtual bidder is not a power plant. The bidding documents built in 3 virtual bidders. The one that absorbed that capacity is the cap bidder, set at 30 USD/kW-month and 65 USD/MWh to bound the auction's monomic price, which combines the 2 charges of a bid: capacity and energy. The report records that its entry at round 33 pushed every monomic price down. Each MW assigned to it is a MW the buyer will have to source elsewhere.
48 bidders took part with 93 technically compliant blocks, and 57 offers were awarded. The awarded monomic price came to 101 USD/MWh at a 0.716 plant factor, after 14 hours and 74 rounds of an iterative descending-price auction. The largest offer, 350 MW of solar with battery storage, starts in 2030. The split between the 2 distributors begins at 55% for Energuate and reaches 50% and 50% from 2033.
Our reading: a buyer that tenders a stepped requirement and reads the result against the final year's total cannot see which year was left uncovered. The PEG-5 model minimized the cost of the whole period, and the whole period is better covered than its first year. Bidders chose their entry year, and 1 in every 5 MW of 2030 was left without a contract.
A Decision System for Capital Allocation makes coverage by year the decision variable rather than the period total. The buyer then prices each year's shortfall before awarding. That is our hypothesis, and it falls if covering the 2030 shortfall costs the same as the 101 USD/MWh contracted. Open Tender 1-2026, which contracts from 2027, will produce that figure.
Anyone weighing PEG-6 decides now. The bidding documents have been on sale since October 6 at 25,000 USD, and clarifications close on March 4, 2027. PEG-6 offers 600 MW from May 1, 2032, almost 5 times the 123 MW shortfall PEG-5 left in that year. PEG-6 covers demand growth rather than the previous tender's residue. The distributors report peak demand on the National Interconnected System of 2,301 MW in 2026, 8.6% above 2025.